There was a lot of testing on the Tampere-Pori/Rauma track section during the autumn – next year, testing will transfer to field testing
Over the past year, the focus on the Tampere–Pori/Rauma track section has been on field work, such as cabling and installation work. Towards the end of the year, the project took a big step forward as various testing could be started in laboratory environment. Next year, the focus will be shifting even more to testing, […]