Field testing has started on the Kouvola-Kotka-Hamina track section

A test locomotive equipped with the European Train Control System will be driven on a closed track section on the Kouvola-Kotka-Hamina line. The purpose is to test the functionality of both the onboard and trackside equipment as well as the traffic control systems. The test track provides experience on ETCS operation in an actual railway […]

The planning for the construction of the EKA track section is progressing on schedule – important lessons learnt are being collected for the benefit of the next planning phase

In the construction planning of the EKA track section, the planning areas are divided into three different entities; Kokemäki-Rauma, Kokemäki-Mäntyluoto and Mäntyluoto-Tahkoluoto as well as Lielahti-Kokemäki. The project is unique, as a lot is being done for the very first time. An example of this is the connection of level crossings to ETCS.   The […]